Orion and Carina carpet replacement
May 21, 2024
Dear residents
Please see below dates for the carpet replacement:
Carina week commencing Monday 17th June (a week to complete each block)
Monday 17th Rip up (one day to complete)
Tuesday 18th Latex 10am - 11am to apply the latex and will take 1 – 2 hours to go off (one day to complete)
Wednesday 19th, Thursday 20th Fitting of carpet and nosings
We have pencilled in Friday 21st June finishing off
Orion week commencing Monday 24th June ( a week to complete each block)
Monday 24th Rip up (one day to complete)
Tuesday 25th Latex 10am - 11am to apply the latex and will take 1 – 2 hours to go off (one day to complete)
Wednesday 26th, Thursday 27th Fitting of carpet and nosings
Friday 28th June finishing off