Orion and Carina carpet replacement


  May 21, 2024

Dear residents

 

Please see below dates for the carpet replacement:

 

Carina week commencing  Monday 17th June (a week to complete each block)

 

Monday 17th Rip up  (one day to complete)

 

Tuesday 18th  Latex 10am - 11am to apply the latex and will take 1 – 2 hours to go off (one day to complete)

 

Wednesday 19thThursday 20th Fitting of carpet and nosings 

 

We have pencilled in Friday 21st June finishing off 

 

 

Orion week commencing Monday 24th June ( a week to complete each block)

 

Monday 24th Rip up  (one day to complete)

 

Tuesday 25th  Latex 10am - 11am to apply the latex and will take 1 – 2 hours to go off (one day to complete)

 

Wednesday 26thThursday 27th Fitting of carpet and nosings 

 

 Friday 28th June finishing off